Gunnison-Crested Butte Regional Airport Remodel Schedule (Summarized)
Project Kick-off: April 5th, 2021
Exterior Site-work: Spring/Summer 2021
- Underground Utilities and West Parking Lot: April - August 2021
- East Parking Lot and Covered Parking: August - October 2021
- Solar Array - November 2021
Phase 1 Terminal Renovation: April - December 2021
- At the end of this phase most of the terminal will be operational including a new security screening area, new hold rooms, jet bridges, baggage claim, restrooms, and food/drink service.
Phase 2 Terminal Renovation: December 2021 - June 2022
- This phase will include completing new escalators to the second floor hold rooms, some exterior finish work, finish work around ticketing counters, and other finishes inside and outside of the terminal.
Final Project Completion: June 2022